At a recent biogas facility, Sentry’s South Dakota Service Division completed specialty piping and equipment installation work to support ongoing facility operations.
Completed work included field measurements for 12-inch stainless piping, shop and field TIG welding, and installation of stainless process piping for final system connections.
The project also included lowering pumps into a 13-foot pit as part of the installation scope.
Sentry’s South Dakota Service Division supports facilities with piping modifications, field welding, equipment installation, and maintenance support across multiple industries.